HRM627, MGMT627 GDB
Page 1 of 1 • Share
HRM627, MGMT627 GDB
Discussion Question:
The project manager of XYZ Company asked a junior team member to develop a PERT Chart for a small project involving four activities – A, B, C and D – using the given relationship:
· Activity A and activity B are done simultaneously
· Activity C starts when activity A is finished
· Activity D starts only when both activities A and B are finished
The junior member worked on it and developed following PERT Chart:
[You must be registered and logged in to see this image.]
Question: Analyze the PERT Chart and discuss, along with reasons, whether it was designed correctly or not.
The project manager of XYZ Company asked a junior team member to develop a PERT Chart for a small project involving four activities – A, B, C and D – using the given relationship:
· Activity A and activity B are done simultaneously
· Activity C starts when activity A is finished
· Activity D starts only when both activities A and B are finished
The junior member worked on it and developed following PERT Chart:
[You must be registered and logged in to see this image.]
Question: Analyze the PERT Chart and discuss, along with reasons, whether it was designed correctly or not.
goli mar- Monstars
- Posts : 24
Join date : 2011-05-23
Re: HRM627, MGMT627 GDB
In my opinion PERT chart is not designed correctly, because the main reason is that, the purpose of this chart is about to achieve Goals on time, but in this chart no activity is getting complete on a single point.
2nd reason is that, if it said that activity A & B will complete, than C will be started, so C & D should remain the same to complete that process parallel, but in this chart D is taking much time to complete that tast
2nd reason is that, if it said that activity A & B will complete, than C will be started, so C & D should remain the same to complete that process parallel, but in this chart D is taking much time to complete that tast
goli mar- Monstars
- Posts : 24
Join date : 2011-05-23
Similar topics
» Mgmt627 Final Term Paper
» Mgmt627 Final Term Paper
» MGMT627 - Assignment No. 01 Solution Spring 2013
» MGMT627 - Project Management GDB Solution Spring 2013
» HRM627 Assignment No. 2 Solution
» Mgmt627 Final Term Paper
» MGMT627 - Assignment No. 01 Solution Spring 2013
» MGMT627 - Project Management GDB Solution Spring 2013
» HRM627 Assignment No. 2 Solution
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|
Yesterday at 9:57 am by Ibad Khan Buledi
» house disrepair claims
Mon Apr 22, 2024 11:23 am by Joshuaadam
» Aloha Planner - Note-Taker
Thu Apr 11, 2024 4:52 pm by ali001
» Streaming Guide Film TV Series
Tue Apr 09, 2024 9:39 pm by ali001
» Apricot Tree Problems & Solutions ????|خوبانی کے پھل کو کیڑا لگنےسے بچانے کا طریقہ ????
Sun Apr 07, 2024 6:28 am by Zamaan Khan
» خوبانی کے پودے کی کاشت گرم علاقوں میں کرنی چاہیے یا نہی
Sun Apr 07, 2024 6:24 am by Zamaan Khan
» New Here
Sun Apr 07, 2024 6:15 am by Zamaan Khan
» Bajta Hua Sochoon Main Koi Saaz Na Aaye Naat
Sun Apr 07, 2024 6:14 am by Zamaan Khan
» Woh Pagal Si Episode 52 to 62 - Top Pakistani Drama
Sun Apr 07, 2024 6:06 am by Zamaan Khan