CS615 - Software Project Management FINAL TERM PAPER

View previous topic View next topic Go down

GMT + 3 Hours CS615 - Software Project Management FINAL TERM PAPER

Post by winnersgroup Wed Mar 02, 2011 7:11 am

. what are the tasks that you perform in project closedown ? (2)
. state any three benefits of weekly status report (2)
list the features of WBS? (2)
what are the advantage of function point (2)
.what are the types of risk (2)
how can material resource rate is calculated? (2)
.define software process & explain it (3)
.write down concept of “time and effort allocation” for project scheduling ? (3)
.when risk is considered in the context of software engineering what conceptual underpinning are always in evidence (3)
what is process line? How many ways a progress line can be displayed? (3)
.list the project planning key tasks used in planning physics (3)
.what are the output that comes from staff acquisition (3)
.why we use WBS?(5)
difference between reactive & proactive risk management (5)
. prepare simple risk analysis table?(5)
winnersgroup
winnersgroup
Fire Breathing Bluebirds
Fire Breathing Bluebirds

Posts : 347
Join date : 2011-02-07

https://virtualposition.forumotion.net

Back to top Go down

GMT + 3 Hours Re: CS615 - Software Project Management FINAL TERM PAPER

Post by winnersgroup Wed Mar 02, 2011 7:11 am

Q 31. what are the tasks that you perform in project closedown ? (2)
Ans: Prepare closedown report
Identify Learning
Identify reusable software components
Create reference material
32. state any three benefits of weekly status report (2)
Ans: Activities during the period
Activities plaaned for next week
Problems.
33. list the features of WBS? (2)
Ans :First, it gives the management an idea about the size and complexity of the
project.
Second, it helps in planning, scheduling, and monitoring a project realistically.
This is possible because all the tasks in the project can be preformed measurable
targets for each task.
34. what are the advantage of function point (2)
Function points are language-and technology-independent. Therefore, you can use
them to estimate any kind of project. They can also be used to estimate the effort,
cost, and schedules of projects that use the Prototyping and Spiral models because
such projects have uncertain user and project requirements.
In addition, you can use function points as a project estimation technique when
you anticipate changes in the middle of a project. These changes may disturb the
estimates if, you had used SLOC to estimate the effort, cost, or size of a project.
The FP estimation uses a subjective and holistic approach for project estimation.
Consequently, the estimates calculated by using the FP are unlikely to be
incorrect.
35.what are the types of risk (2)
Ans: A software project encounters two types of risks, development process risks and
product- related risks. Some of the development process risks are developer
errors, natural disasters, disgruntled employees, and poor management objectives.
Some project related risks are incomplete requirements, unclear project
deliverables and objectives, and complexity of the product.
36.how can material resource rate is calculated? (2)
37.define software process & explain it (3)
Ans: When you build a product or system, it’s important to go through a series of
predictable steps – a road map that helps you create a timely, high-quality
result, The road map that you follow is called a ‘software process’
A software process provides the framework from which a comprehensive plan
for software development can be established.
38.write down concept of “time and effort allocation” for project scheduling ? (3)
Ans: each activity in a software project needs a certain amount of time and effort
for completion. To manage the project, you assign start and end dates to each
activity. You also need to allocate appropriate effort to each activity. Most
software projects operate with time and effort constraints. Therefore,
managing within the available resources is very important for a software
project manager
39.when risk is considered in the context of software engineering what conceptual underpinning are always in evidence (3)
Ans: – The future is our concern – what risks might cause the software project to go
awry?
– Change is our concern -how will changes in customer requirements,
development technologies, target computers, and all other entities connected
to the project affect timeliness and overall success?
– Last, we must grapple with choices - what methods and tools should we use,
how many people should be involved, how much emphasis on quality is
"enough"?

40.what is progess line? How many ways a progress line can be displayed? (3)
To track a project plan, you first view the progress of a project. You can view the
progress of a project by applying progress lines to the tasks in the project. You
can display progress lines in three ways,
41.list the project planning key tasks used in planning physics (3)
Ans: 1. Set goal and scope
2. Select lifecycle
3. Set organization team form
4. Start team selection
5. Determine risks
6. Create WBS
7. Identify tasks
8. Estimate size
9. Estimate effort
10. Identify task dependencies
11. Assign resources
12. Schedule work
42.what are the output that comes from staff acquisition (3)
Ans: i. Project staff assigned. The project is staffed when appropriate people have been
reliably assigned to work on it. Staff may be assigned full time, part time, or
variably, based on the needs of the project.
ii. Project team directory. A project team directory lists all the project team
members and other stakeholders. The directory may be formal or informal, highly
detailed or broadly framed, based on the needs of the project.
43.why we use WBS?(5)
Ans: Using a WBS provides a number of benefits to the management and to the
development teams.
First, it gives the management an idea about the size and complexity of the
project.
Second, it helps in planning, scheduling, and monitoring a project realistically.
This is possible because all the tasks in the project can be preformed measurable
targets for each task.
winnersgroup
winnersgroup
Fire Breathing Bluebirds
Fire Breathing Bluebirds

Posts : 347
Join date : 2011-02-07

https://virtualposition.forumotion.net

Back to top Go down

GMT + 3 Hours Re: CS615 - Software Project Management FINAL TERM PAPER

Post by winnersgroup Wed Mar 02, 2011 7:12 am

I took my CS 615 exam today at 2:00 PM .
Paper was very strange . :p I can't say that it was conceptual or out off syllabus but puzzle Sad........Past papers us sary m sy just 3 MCQs ay thy Sad(

(in short hr Qs ghumma k rakhny wala tha :p)

Total Marks were 75, 30 MCQs each of 1 mark and 15 short and long Question were there.
3 question were of 5, 5 marks as subjective.

All sbjective and short Qs was related to Risk and life cycle models (so plz focus on these topics if you have to go to take the CS615 exam )
winnersgroup
winnersgroup
Fire Breathing Bluebirds
Fire Breathing Bluebirds

Posts : 347
Join date : 2011-02-07

https://virtualposition.forumotion.net

Back to top Go down

GMT + 3 Hours Re: CS615 - Software Project Management FINAL TERM PAPER

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

Permissions in this forum:
You cannot reply to topics in this forum